Sand pumping halted: 'A challenge to satisfactorily complete work prior to deadline'

Do you have a news tip? Click here to send to our news team.

Major milestone reached for cable-stay bridge

A long-awaited Sunshine Coast landmark is nearing completion. The $27 million cable-stay bridge across Lake Kawana at Birtinya is expected to open in June or More

Coastal suburb surges into top tier of unit sales

A fast-growing Sunshine Coast area has climbed into the top three suburbs for unit sales in Queensland. Maroochydore was ranked third in the latest Property More

Work starts on $300m apartment towers

Construction has started on a mixed use development with 179 apartments in the heart of a Sunshine Coast beach town. Work is underway on the More

Coast building approvals rise despite cost pressures

Sunshine Coast building approvals have surged even as Queensland’s construction industry warns that rising materials costs and supply chain disruptions are increasing pressure on More

Prominent fast-food site set for auction

A fast-food investment on the Sunshine Coast is set to be brought to market, giving buyers access to a high-growth area. The newly built KFC More

Hundreds of new trees to bolster wildlife corridor

More than 500 native tree seedlings have been planted at a 7.5 hectare property to provide vital refuge for wildlife. Hinterland Bush Links’ Roving Restorers More

Works to replenish sand on a popular off-leash dog beach have been halted amid challenging environmental conditions and timeframe constraints.

Noosa Council said in a press release it had made the “difficult decision” to stop work on the project at what is known as Doggy Beach at the Noosa Spit, near the Noosa River mouth.

The release said it was decided, in consultation with the contractor engaged to do the project, to stop the dredging work, due to the challenging nature of that section of the river and the likelihood of it not being completed before the permit deadline.

Want more free local news? Follow Sunshine Coast News on Facebook, LinkedIn and Instagram.

“The work needed to be completed by late September to comply with the environmental permit and, in discussions with the contractor, it was going to be a challenge to satisfactorily complete the work prior to the deadline,” council’s acting infrastructure services director Bryan O’Connor said.

Under the permit, work could only be conducted from April to September, due to seasonal migratory shorebirds.

The council will continue to investigate options to complete the sand nourishment work when possible.

The planned works, which are now on hold.

The section will now reopen to the public. The dog beach and a part of the car park next it closed while the works were being completed.

Walkers, swimmers and all recreational marine craft (powered and non-powered) had been asked to avoid the area.

The $1 million project aimed to pump sand from designated collection zones in the river channel and re-nourish the shores of the area.

“The dog beach at Noosa Spit is an important site supporting key recreational and social activities, and forms part of an artificially constructed river training and coastal defence strategy for the Noosa River mouth,” mayor Clare Stewart said in May when announcing the project.

“Over the years, this defence system has been slowly eroding, seeing trees and pathways washed away.”

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name and suburb.

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share