100% Locally Owned, Independent and Free

100% Locally Owned, Independent and Free

Works to cause changes to traffic and pedestrian movements

Do you have a news tip? Click here to send to our news team.

Seafood supply assured at Easter despite fuel challenges

Sunshine Coast fishing operators say an abundant supply of fresh, local catches will be available for Easter despite fuel shortages. Rockliff Seafood PR manager Vanessa More

Beachgoers urged to film and report driving offences

Visitors to some of Queensland's most popular 4WD and camping beaches have been encouraged to record and report misbehaving motorists during the Easter school More

Sami Muirhead: whip out those Easter buns

Finally, it is time to eat hot cross buns. When you think about it, they should be called ‘cold cross buns’ or even ‘room More

Ashley Robinson: fond memories help ease loss

The past few weeks have been a test of my faith: firstly, with the tragic loss of 18-year-old lifesaver Joe Tolano; and, just a More

B2B: report work vehicle private use correctly

The Australian Tax Office (ATO) is actively using sophisticated data analytics to target employers who fail to report, or incorrectly report, fringe benefits. ATO compliance More

Dog owners warned to renew registrations or face fine

Dog owners whose pet registrations expired between June 1 and November 30 2025 are being warned to renew now or face a $333 fine. Noosa More

Noosa Council has moved to secure the long-term safety of a landslip-affected area in Sunrise Beach.

The decision came during the Ordinary Meeting on February 19, when councillors voted unanimously to award Sunshine Civil Solutions Pty Ltd the contract, valued at $2,492,858.96.

As part of the Sunshine Creek Landslide Stabilisation Project, the contract allows the council’s chief executive officer to negotiate and execute the agreement, with authority to adjust the contract by up to 17.57 per cent of the project budget if required.

The stabilisation project targets slope damage near Ross Crescent in Sunrise Beach. Although temporary repairs were previously carried out, ongoing monitoring by experts highlighted the need for a more substantial fix to ensure the area’s stability.

Works are scheduled to begin in early March, and include: removal of existing materials from the site; stabilisation of the embankment to protect the footpath and surrounding infrastructure, including stormwater systems and utilities; and removal of non-compliant beach accesses, while Beach Access 35 will remain unchanged.

Want more free local news? Follow Sunshine Coast News on Facebook, LinkedIn and Instagram, and sign up for our FREE daily news email.

Steep slopes and nearby utilities mean construction access will be limited, resulting in changes to traffic and pedestrian movements.

Affected areas in Sunrise Beach. Picture: Noosa Council.

Residents and visitors can expect: a road closure near the pathway entrance; closure of the pathway between Sobraon Street and Adams Street/Ross Crescent; reduced speed limits and active traffic control in the area; and short-term, intermittent closures of Beach Access 35 for public safety.

Construction is expected to be completed by June 30, which is dependent on weather and site conditions.

Standard working hours will be 6am to 6pm, Monday to Friday, with occasional Saturday work.

Council has urged parents to plan safe alternative routes for children who use the pathway and promised further updates once the contractor finalises construction details.

The aerial imagery in this story is from Australian location intelligence company Nearmap. The company provides government organisations, architectural, construction and engineering firms, and other companies, with easy, instant access to high-resolution aerial imagery, city-scale 3D content, artificial intelligence data sets, and geospatial tools to assist with urban planning, monitoring and development projects in Australia, New Zealand and North America.

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share