Double the price: another costs hike hits region's transport plans

Do you have a news tip? Click here to send to our news team.

Lease pressures mount as small businesses navigate rising costs

Small business owners in some of Noosa’s most popular commercial precincts are facing mounting financial pressure, with typical leases along Gympie Terrace and Noosa More

Residents help shape plan for multi-faceted park

A concept plan for a new district park with four distinct areas is being refined after strong community input, with almost 160 submissions helping More

Cyclists take on gruelling challenge for kids in care

Cyclists are set to take on some of the region’s toughest hills in the 76km Buderim9 Challenge on November 23, raising money for The More

Ashley Robinson: the dogged pursuit of the truth

There is an old saying: “Men occasionally trip over the truth. They quickly get up, dust themselves off and pretend it never happened.” I reckon More

Photo of the day: heavenly rays

Lesley Evans snapped this photo of sunlight penetrating clouds over Kings Beach, Caloundra. If you have a photo of the day offering, email photo@sunshinecoastnews.com.au. Photos More

Teen charged after e-bike crash kills eight-year-old

A teenager has been charged over an e-bike crash that killed an eight-year-old boy and sparked calls for law reforms. The 15-year-old boy was arrested More

A budget blowout has cast uncertainty over another key transport project on the Sunshine Coast.

It was initially expected to cost $550.8 million to deliver the Beerburrum to Nambour Rail Upgrade (Stage 1) from Beerburrum to Beerwah, but it now has a revised price tag of $1.0042 billion and no guarantee of full funding.

Work has already started on the project, including the realignment of Steve Irwin Way, the opening of new train station car parks and construction of a bus interchange.

The new costings also cast further doubt on the proposed Stage 2 to Nambour.

It comes after costs estimates soared for other transport projects in the region, including the $12 billion Direct Rail Sunshine Coast and the essentially abandoned $750 million Mooloolah River Interchange Upgrade.

A Transport and Main Roads spokesperson said the B2N Rail Upgrade would be of great benefit.

A map of public transport plans, including the B2N Rail Upgrade, in orange.

“Once complete, it will increase capacity, improve reliability, and reduce travel times for passengers and freight in the growing Sunshine Coast region,” they said.

“Works are progressing well on Stage 1, with preconstruction and design works currently underway for the main construction works.

“These (main) works will include duplication of the North Coast Line between Beerburrum and Beerwah, address level crossings on the alignment, expand the park ‘n’ ride facility in Beerburrum and undertake associated road works.

“In preparation for the main works, early works were completed with the opening of new park ‘n’ ride facilities at Landsborough and Nambour (300 car parks at Landsborough and 50 car parks at Nambour) and a new bus interchange at Landsborough station in August.

“A section of Steve Irwin Way has also been realigned near Glass House Mountains to make way for the duplicated rail line.”

The spokesperson said detailed design for Stage 1 (an estimated 13km stretch) was expected to be completed this year, with main construction works to follow, but added that costs had blown out and the government would consider its next steps.

“The Australian and Queensland governments have committed $550.8 million towards the B2N Stage 1,” they said. “A revised project cost of $1004.2 million ($1.0042 billion) is subject to further consideration.”

The spokesperson revealed why it had become much more expensive and said further studies could provide more clarity on its future.

“With the significant labour and material cost escalations since the business case was complete and funding committed, completing detailed design will provide more certainty on expected costs,” they said.

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name and suburb.

The spokesperson said Stage 2 of the B2N (an estimated 37km stretch from Beerwah to Nambour) was being looked at.

“Future stages of B2N will be investigated as part of the $6.25 million duplication study, jointly funded by the Australian and Queensland governments,” they said.

The Nambour train station is at the end of the line for the proposed B2N project. Picture: Steele Taylor

“This study will assess options to improve operations, efficiency, accessibility to rail services, and meet future freight needs, including refining the scope for future stages of the B2N project beyond the scope of Stage 1.

“The study is proposed to be undertaken in parallel with delivery of the Direct Sunshine Coast Rail Line to ensure that network wide operations and demand profiles in the Sunshine Coast region are being considered in a staged and logical way.”

Rail Back on Track spokesperson Jeff Addison lamented the lack of progress on the line and said it should be duplicated all the way to Nambour, as soon as possible.

“It needs to happen now,” he said.

The new park ‘n’ ride at Nambour. Picture: Steele Taylor

“(It needs to happen) for the economically advantageous freight benefits.

“Improvements to passenger rail services are a nice collateral advantage.

“The rail is restricted by short passing loops along its predominant single track that restricts the length of freight trains from Brisbane up to north Queensland.

“We can only run 650m long trains.

“The state government has known about this critical freight bottleneck for decades but the only action is yet another study which will likely never be actioned, if past performance is any guide.”

Like stories that inform, connect and celebrate the Sunshine Coast? So do we. Join an independent local news revolution by subscribing to our FREE daily news feed at the bottom of this article.

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share