EOI campaign launched to begin underground tunnelling on $14.2b project

Do you have a news tip? Click here to send to our news team.

Speed reduction, crossings on way to town centre

A speed limit change, raised crossing and other street safety upgrades are about to be introduced in the middle of a town. The state government More

Prominent farming family lists rare waterfront property

A rare waterfront block of three units is up for sale on the Sunshine Coast. The property, at 10 Maloja Avenue, Caloundra, known as Sunset More

Families left in limbo as au pair visas stall

Three Sunshine Coast mothers are facing disruptions to their childcare, businesses and household finances as Working Holiday Maker (WHM) visa delays continue. Tamsyn, Sophie and More

Lifeguard funding push gathers pace

Noosa Council is calling on the Queensland Government to help fund its lifeguard services, with millions of people using the shire's beaches each year. Councillors More

Teen takes women’s health app to national cyber stage

A 15-year-old Sunshine Coast student has taken an idea born from her own experience to one of the country’s leading cyber events, putting her More

Illegal e-bikes, e-scooters seized and crushed

Hundreds of illegal e-mobility devices have been seized around Queensland since new laws took effect, with the first confiscated devices crushed and destroyed. The actions More

A significant step has been taken in a project set to inject tens of millions into the regional economy, with a call for expressions of interest to begin underground tunnelling on the Borumba Pumped Hydro underway.

The EOI for underground works marks the first step in the most significant program to be delivered during the exploratory works phase of the project.

The package will involve the excavation of soil and rock utilising controlled blast and drilling methods, rather than tunnel boring machine, to form a D-shaped tunnel leading to the proposed site of the underground powerhouse cavern.

This tunnelling will complement surface geological investigations, which together will provide a detailed understanding of ground conditions to inform detailed design of the project and how it is best delivered.

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name and suburb.

The works will be accompanied by the required environmental approvals and, once complete, the excavated tunnel will be repurposed to become a permanent cable tunnel.

The $14.2b pumped hydro energy project, in the Sunshine Coast Hinterland, is being delivered by public energy company Queensland Hydro.

Queensland Hydro CEO Kieran Cusack; Energy, Renewables and Hydrogen Minister Mick de Brenni and Plumbing and Pipe Trades Employees Union organiser Luke Barden.

“Queensland Hydro is pleased to release this EOI to the market,” CEO Kieran Cusack said.

“We’re excited about this release because it’s the first major package of works since we launched our industry engagement program in July, with three industry events held in Brisbane, Sunshine Coast and Gympie.

“Attendees came from a broad range of industry including contractors, local suppliers, service suppliers, consultants, equipment suppliers and potential industry partners.

“We’ve been working with industry to ensure we attract the best partners for the project while creating opportunities for local industry involvement.

“Queensland Hydro will work with the successful contractor to maximise opportunities for local and Indigenous businesses and workers to be prepared for, and access opportunities on the exploratory works program.”

The EOI release follows the Coordinator-General’s coordinated project declaration on October 12, signalling the start of the assessment of social, economic and environmental matters before the Borumba project’s main works can begin.

The first of the Palaszczuk Governments two foundational hydropower energy storage projects, the 2000MW Borumba project will charge up from excess wind and solar generated in the state’s southeast to keep the lights on for up to two millions households.

Once underway, the project’s main works will create more than 2000 jobs during construction, and boost the regional economy by tens of millions.

Borumba Dam, west of the Sunshine Coast.

Minister for Energy, Renewables and Hydrogen Mick de Brenni said the project would drive economic growth and help deliver cleaner energy.

“Experts and responsible leaders around the world are recognising the critical role of pumped hydropower in unlocking the capacity of renewables and delivering the clean energy transition,” he said.

“Pumped Hydro offers a trifecta of opportunity by driving sustainable economic growth, bringing wealth and equality to more communities, and combating climate change.

“This next phase of works on the Borumba Pumped Hydro project shows how committed Queensland Hydro and the Palaszczuk Government are to delivering this key clean energy project.

“Throughout construction the project will deliver a significant uplift in jobs and a boost to the regional economy, and once completed it will also deliver cleaner, cheaper and more secure energy for all Queenslanders.

“As the cornerstone of the Queensland Energy and Jobs Plan, our pumped hydro projects will ensure Queensland remains on track to meeting its renewable energy targets, while ensuring we can continue to put ongoing downward pressure on electricity bills for years to come.”

Scroll down to SUBSCRIBE for our FREE news feed, direct to your inbox daily.

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share