Bustling intersection set for upgrade during stage one of $9.8m Tewantin Bypass project

Do you have a news tip? Click here to send to our news team.

Police investigate suspicious vehicle fire

Queensland Police have declared a crime scene after responding to a vehicle fire at the southern end of the Sunshine Coast. Police and emergency services More

Heavy smoke spreads across southern Coast

Heavy smoke from a hazard reduction burn is affecting parts of the southern Sunshine Coast, with the smell reaching coastal areas of Caloundra. The Queensland More

Preferred option revealed for key intersection upgrade

A busy junction is set for an overhaul aimed at improving safety, easing congestion and addressing community concerns. Planning is complete for the Landsborough-Maleny Road More

Revamp starts on bus zone with ‘significant safety issues’

An upgrade to improve safety and traffic management is underway on a school bus zone. Work has started on an overhaul of the Maroochydore State More

Mum leads petition to open school grounds after hours

A Sunshine Coast mother is behind a push for Queensland state school grounds and playgrounds to be opened to the public after hours. Jennifer Brunton, More

Whale alarm trial on shark nets underway at main beach

New acoustic devices are being tested at a renowned holiday beach to determine whether sound can help humpback whales avoid shark control nets. The state More

Work is about to start on the first stage of the Tewantin Bypass, clearing the way for a new roundabout at a busy intersection.

Noosa Mayor Clare Stewart said the design work had identified the alignment of the junction at Cooroy-Noosa Road and Beckmans Road, allowing vegetation clearing and relocation of energy and water infrastructure to start.

“Seeing this project start to take shape after so many years is an exciting milestone,” Mayor Stewart said.

“The preliminary design for the intersection upgrade has enough detail to locate where vegetation will need to make way for the new roundabout and relocation of utilities.

“We have engaged fauna and flora specialists to give the project team advice about the best way to manage this process to minimise the environmental impacts.

“Plants and shrubs will also be planted to offset any vegetation that needs to be removed as part of the project.

“Once the area is clear, Energex and UnityWater can relocate services. Getting this work completed early cuts down the time it will take to complete the major intersection upgrade once design is complete.”

Transport and Main Roads Minister Mark Bailey said the $9.81 million project was being jointly delivered by the state and Noosa council under the Queensland Government’s $400 million road stimulus package.

“This Palaszczuk Government project is one of hundreds of road upgrades being delivered across Queensland to supercharge the economy through the COVID-19 recovery,” Mr Bailey said.

“The new, two-lane roundabout at Cooroy-Noosa Road and Beckmans Road was a top priority for the community and we are getting on with the job of delivering it and supporting jobs for local people along the way.”

Follow Sunshine Coast News on Facebook.

Mr Bailey thanked Noosa MP Sandy Bolton for her work in representing the community and driving the project forward.

“Sandy Bolton has been a strong advocate of the Tewantin Bypass, and instrumental in getting the project to the stage it is today,” he said.

Ms Stewart said vegetation clearing was the first part of the project and would be followed by relocation of services, which would take place in coming months.

“While a lot of the work will take place off Beckmans Road, some will be on or near the existing road, and keeping workers and motorists safe will be a priority,” she said.

Stay up-to-date with local news by subscribing to our FREE daily news bulletin. Simply plug in your email at the top of this article.

“Lower speed limits will apply, and motorists are reminded to take note of changed traffic conditions and any directions given by traffic control.

“Council will also post updates to Facebook to let motorists and locals know when to expect changed traffic conditions.

“We thank the community for their patience while this important project is underway.”

Project design is expected to be complete by June, with main construction to start later this year, weather and construction conditions permitting.

The proposed Tewantin Bypass involves improving the link between Eumundi-Noosa Road and Cooroy-Noosa Road.