Key tunnelling and surface works packages for energy project remain on hold

Do you have a news tip? Click here to send to our news team.

Fire survivor breaks silence in new memoir

A Sunshine Coast mother whose husband tried to murder her and their two young children by setting fire to the family home is speaking More

Youth housing complex contract awarded

A planned housing complex for vulnerable young people has moved a step closer after a construction contract was announced. The state government's Sunshine Coast Youth More

Soldier drives Army’s new Boxer

A former Sunshine Coast groundsman who once got around work in a golf buggy is now driving one of the Australian Army’s newest armoured More

Veteran charts course for wellbeing

A former soldier’s specialised boating initiative is helping current and former defence force and emergency services personnel improve their wellbeing and reconnect with others. Sunshine More

Consultation underway on next stage of bypass

Public feedback is being sought on the next phase of key road project, including new lanes and changes to a busy intersection. The state government More

Parents reach out amid hidden struggles

Scores of Sunshine Coast parents have sought specialist support this year as they navigate the mental health pressures of pregnancy and life with a More

Queensland Hydro is reviewing how work on a multibillion-dollar project is sequenced as it prepares an updated business case for the state government.

The state-owned company is developing the Borumba Pumped Hydro Project near Imbil to provide long-duration energy storage.

A Queensland Hydro spokesman said activities were being reviewed to ensure they were appropriately sequenced and supported by “robust governance and assurance”.

The comments come after the Mary River Catchment Coordinating Committee welcomed a Queensland Hydro move to suspend procurement for exploratory tunnelling and drilling.

Committee chairman Ian Mackay said it provided an opportunity to pause and reconsider the project’s economics and need.

“We hope this recent announcement is the result of a rethink by the state government, which inherited the project from its predecessor,” he said.

“Given the economics, we feel that calling a halt until a thorough business case is complete is an astute move.”

Queensland Hydro did not directly answer Sunshine Coast News’ questions about  exploratory tunnelling being put on hold.

However, a procurement notice, published on October 22, states the exploratory tunnelling and drilling package was suspended and no contract was awarded. Procurement for a separate surface civils package was also suspended.

Lake Borumba is the site of a massive energy project. Picture: Shutterstock

Queensland Hydro’s project web page said the Borumba project was in the investigation and planning phase, with main works yet to commence.

The proposal would involve reservoirs connected by tunnels and an underground power station, allowing energy to be stored and generated when needed to help support a reliable and secure electricity system.

The current program includes geotechnical investigations, environmental studies, community engagement and economic assessment.

The results will inform an updated business case to be provided to the state government in 2027.

Any future main construction, including reservoirs, tunnels and an underground power station, would require separate approvals and government decisions.

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name and suburb.

A Queensland Hydro spokesperson said the program of works was being reviewed as planning progressed.

“Queensland Hydro continues to update the Borumba project’s development and delivery approach.”

“Activities are being reviewed to ensure they are appropriately sequenced and supported by robust governance and assurance, and refinements to workstreams are required as appropriate for this stage of operations.”

Mr Mackay said the committee supported replacing the existing Borumba Dam wall as a separate dam safety project, and believed it should proceed independently of the pumped hydro proposal.