Temporary cofferdam complete as Lake Macdonald Dam upgrade reaches major milestone

Do you have a news tip? Click here to send to our news team.

Teen charged after allegedly stolen car crashes

A teenager has been charged after an allegedly stolen car crashed in Nambour this morning. Police allege a white Honda Civic was stolen from an More

Commercial precinct approved beside heritage landmarks

A new commercial precinct that will be located beside two heritage-listed buildings in the Sunshine Coast hinterland has been given the green light. Sunshine Coast More

Coast set to host football knockout matches at 2032 Games

The Sunshine Coast is in line to host some of the main football matches during the 2032 Games. The state government revealed that knockout games More

Farm turns scraps into future crops

A Sunshine Coast farm is tackling food waste with its new Feed Your Food program, turning household scraps into compost to grow future crops. Located More

Leaders unite to tackle school bullying

Caloundra has hosted the latest anti-bullying roundtable as Queensland’s $33 million program brings community leaders together to find solutions. Sunshine Coast community leaders, educators, students More

Firefighters scale mountain in overnight rescue operation

An injured hiker has been rescued from the southern face of Mt Beerwah after spending the night on the mountain during a complex emergency More

A temporary dam has been completed as part of the Lake Macdonald Dam Improvement Project, paving the way for the next critical phase of works to proceed.

The construction of the cofferdam marks the end of Phase 1 of the upgrade, with works to now move into Phase 2: the demolition of the existing spillway and embankments.

Demolition was due to start late last week and will involve 24-hour continuous operations for about 15 days, weather permitting.

The accelerated construction approach is designed to protect the site and maintain safe lake levels and downstream flows throughout the demolition period.

Seqwater executive general manager infrastructure planning and capital delivery Sarah Dixon said the project was making strong and steady progress on the dam upgrade.

“Completing the temporary cofferdam is a major achievement and positions us well to safely transition into next phase of construction,” she said.

“While weather conditions can change, we have well-established plans in place to pause and secure the site should conditions shift unexpectedly throughout the demolition phase. Safety remains our priority every step of the way.”

During the continuous works period, specialist crews will monitor operations and environmental controls around the clock.

Seqwater and construction partner John Holland Group are continuing to work closely with local residents, including one-on-one engagement with adjacent residents.

“We appreciate the patience and cooperation of our neighbours. Completing this work safely and quickly is our priority,” Ms Dixon said.

Once demolition is completed, construction of the new dam will begin. The new design includes a split-level concrete spillway, a lower ogee crest at the original lake level and an upper labyrinth spillway to safely manage higher flows.

The project will support more than 150 jobs throughout construction and aims to ensure the dam meets modern engineering standards, continues to operate safely and provides long-term water security for the region for generations to come.

“The Lake Macdonald Dam Improvement Project is part of Seqwater’s Dam Improvement Program, an important investment to ensure our vital infrastructure continues to remain safe and reliable for future generations,” Ms Dixon said.