First workers on $14b Lake Borumba hydro project to be housed in temporary camps

Do you have a news tip? Click here to send to our news team.

Key pathways and bus stops receive upgrades

Pedestrians and public transport users at the northern end of the Coast can now get around safer and more easily thanks to upgrades to More

Coast construction group marks half a century building legacies

A Sunshine Coast construction group is marking a significant milestone in its history of creating homes and communities. Murphy Group is celebrating 50 years since More

Photo of the day: river reflections

“Thought you might like this image from down at the Cod Hole on the Maroochy River. Just the perfect winter morning,” writes Chris Perkins. If More

Tourist icon up for sale with $80m price tag

A revitalised Sunshine Coast tourist precinct has been listed for sale by its long-term owners, with a reported price of more than $80 million. Originally More

Fieldwork and local insights guide huge rail project

Environmental surveys are well underway for a multibillion-dollar rail project on the Sunshine Coast, with experts gathering ground data and local knowledge to help More

Campground visitors decrease despite bumper forward bookings

A collection of caravan parks has recorded fewer visitors over a 12-month period, citing an industry-wide “softening” and rain as contributing factors. Noosa Council released More

Two temporary camps will be set up to house the first workers on a $14 billion hydro project west of the Sunshine Coast.

The short-term camps will accommodate workers who will undertake exploratory works and provide essential geotechnical data to inform the approvals and technical design of the Borumba Pumped Hydro Energy Storage project.

Related story: Jobs bonanza as key details of $14b hydro project revealed

Construction of the two camps will require about 40 workers and provide accommodation for up to 168 workers throughout the exploratory works stage of the project.

“Accommodation is a challenge across the state, which is why it’s critical that we ensure this workforce has a roof over their head while this vital exploratory work is underway,” Deputy Premier Steven Miles said.

“Additionally, it means progressing this project won’t impede on housing supply for Gympie and surrounds.”

The mega project is a cornerstone of the state government’s Queensland Energy and Jobs Plan, and critical to meeting the state’s target of 70 per cent renewable energy by 2032.

A map showing the location of the two temporary workers’ camps.

The camps will be operated 24/7 and include some recreational facilities such as a gym and outdoor exercise areas. They will be located on freehold land, with one site owned by Queensland Hydro and the other owned by the Queensland Government.

The camps are being developed with input from community and unions to ensure the best conditions for workers.

Delivery of the camps is subject to the state government’s Buy Queensland procurement policy, which means locals will be sought to help build and operate the camp and associated services.

“The construction and operation of the camps will offer service opportunities for businesses in the local region,” Queensland Hydro CEO Kieran Cusack said.

“There are many local economic benefits of the project and local jobs being created and supported. We already have been working with local industry to ensure they are fully aware of the opportunities in our upcoming procurement packages.”

Queensland Hydro CEO Kieran Cusack; Energy, Renewables and Hydrogen Minister Mick de Brenni and Plumbing and Pipe Trades Employees Union organiser Luke Barden.

Future longer-term project camps will offer an opportunity to Borumba Stakeholder Reference Group members to consider broader tourism and affordable housing options as part of the legacy approach to the project.

The Queensland Government and Queensland Hydro are also in the final stages of developing a community benefits framework for surrounding local communities.

The project will eventually require up to 2000 construction workers.

The state government is investing $183.7 million in the 2023-24 budget with Queensland Hydro to progress the project.

“We know the Borumba project will create 2000 jobs and, once complete, this also means more, good jobs in renewables long into the future,” Mr Miles said.

Lake Borumba is the location of choice for a massive hydro project.

Member for Caloundra Jason Hunt said the project would benefit the Sunshine Coast.

“It’s the workers and businesses of our growing Sunshine Coast region that will play a leading role in building Borumba, one of the most important energy projects in the nation,” he said.

Member for Nicklin Rob Skelton said the project would store enough of Queensland’s clean solar and wind to power two million homes.

“Australians everywhere are looking to us to not only provide reliable renewable energy, but to be a reliable leader that is taking real action on the national energy and climate transition,” he said.

Help us deliver more news by registering for our FREE daily news feed. All it requires is your name and email at the bottom of this article.

Subscribe to SCN’s free daily news email

This field is hidden when viewing the form
This field is for validation purposes and should be left unchanged.
[scn_go_back_button] Return Home
Share