100% Locally Owned, Independent and Free

100% Locally Owned, Independent and Free

Two sites remain in running for millions of cubic metres of dredged sediment

Do you have a news tip? Click here to send to our news team.

Veteran charts course for wellbeing

A former soldier’s specialised boating initiative is helping current and former defence force and emergency services personnel improve their wellbeing and reconnect with others. Sunshine More

Your say: homeless camp closure, rail plans and more

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name More

Luxury apartments sell as $150m project progresses

Several luxury apartments have been sold as construction of a $150 million hotel and residential tower reaches a key milestone. About 30 per cent of More

Swans shake up AFL draft by snaring Murray

Sydney have swung the biggest surprise of the AFL draft's opening night, poaching Brisbane academy prospect Caylen Murray, who honed his skills on the More

Councils lose safe parking bid for homeless

The Queensland Government has rejected a safe parking pilot for people sleeping in vehicles, despite local councils backing a statewide program. Noosa Shire Council and More

Region among hardest hit by melanoma

Hundreds of Sunshine Coast residents have been diagnosed with melanoma in a single year, with Cancer Council Queensland identifying the region as one of More

An area off the Sunshine Coast is no longer being considered as a potential site for placing dredged sediment from a large-scale Port of Brisbane project.

The Northern Deepwater zone, about 10km east of Caloundra was a site of interest for the proposed Channel Enhancement Project.

The multibillion-dollar CEP could include dredging about 96.5 million cubic metres of material to widen, deepen, and realign sections of the existing shipping channel between the Sunshine Coast and Brisbane, plus the “beneficial reuse and disposal of dredged material”.

The Northern Deepwater zone was among a handful of proposed Dredge Material Placement Areas, which would accommodate dredged sediment like sand and mud, shifted by a dredge vessel.

But a project update stated that the site was no longer being considered.

“The proposed DMPA options shown in the Initial Advice Statement, at Northern Deepwater (offshore from Caloundra) and Juno Point (proposed reclamation on the northern bank of the Brisbane River) have now been ruled out and will not be progressed further as part of the EIS (Environmental Impact Study) process.”

The location of the Northern Deepwater area.

A PoB spokesperson told Sunshine Coast News this month that there was a preferred location, and reiterated that dredged material would not end up off the Sunshine Coast.

“Four DMPAs were identified for initial assessment. Only two remain under active consideration: Fisherman Islands Future Port Expansion 2 (FPE2) and Old Channel.

“The Port of Brisbane has made regulators aware its singular preference is for an FPE2, as that involves the construction of an enclosed rock wall, which is the most environmentally sensitive way to handle dredged sediments, as we do currently in the existing Future Port Expansion area).

“Therefore, there are no material placement sites near the Sunshine Coast under consideration.”

A large dredger at work. Sand and mud could be shifted from the shipping channel to a designated placement area. Picture: Shutterstock.

But dredging could occur off the Sunshine Coast, where the end of the shipping lane could be made deeper and wider.

A drilling barge has been off the coast of Caloundra, doing marine geotechnical investigations in the North-West Channel as part of the proposed CEP.

The investigations are also being undertaken at multiple sites between the Sunshine Coast and Brisbane from June until September.

Help us deliver more by registering for our FREE daily news feed. All it requires is your email at the bottom of this article.

The jack-up barge Ocean Driller II in Moreton Bay.
The jack-up barge Ocean Driller II has been off the southern coast of Caloundra, investigating the bay surface in the North-West Channel.

The PoB spokesperson said the CEP could make a significant difference to the state.

“The CEP is a proposed 25-year infrastructure program of works, aimed at preparing the port for future trade and population growth in South-East Queensland,” the spokesperson said.

“The CEP is being designed to ensure the primary shipping channel remains safe, efficient and capable of supporting larger, modern vessels into the future.”

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share