Mooloolaba traffic frustration eases with completion of new lanes on Walan Street

Do you have a news tip? Click here to send to our news team.

Housing tenant loses pet in blaze

A man has been taken to hospital and a dog is dead after a fire in a duplex at Cooroora Street, Dicky Beach. Queensland Fire More

‘Well-known operators’ locked in as precinct nears completion

Work is well underway on a mixed-used complex that is set to include a variety of food and beverage options, health clubs and other More

Police alerted after mayor used by online scammers

The mayor of the Sunshine Coast is urging people to be alert on social media amid revelations fake accounts have been set up in More

Fishing report: a wet one but fish will still be biting

After a few picture-perfect weeks, the gloomy weather has returned, with showers predicted for the long weekend. Windy conditions will make offshore fishing tricky, so More

B2B column: common asset protection a matter of trust

Discretionary family trusts aren’t just for the super wealthy. They are a common asset protection and tax-minimisation tool for thousands of Australian families. They often More

Photo of the day: cloud blanket

Veronica Jenkins photographed Mount Ninderry on a cloudy day. If you have a photo of the day offering, email photo@sunshinecoastnews.com.au. Photos must be horizontal/landscape and More

A key road in the heart of Mooloolaba has been widened to four lanes, marking the completion of another stage of a major transport project to address congestion in the tourism precinct.

The $8.5 million upgrade to Walan Street, between Venning Street (the Coles shopping centre) and Smith Street, completes stage one of the Mooloolaba Transport Corridor Upgrade project.

The vital milestone will enable the next phases to go ahead which include widening Brisbane Road – the gateway to Mooloolaba – to four lanes, a new bridge over Mayes Canal and other intersection and landscape improvements.

Division 4 Councillor Joe Natoli said the Mooloolaba Transport Corridor Upgrade was an important transport project to tackle the frustrating traffic jams and delays during peak periods and to cater for future growth.

“We’re preparing now for the anticipated growth in traffic generated by residents, businesses and the attraction of Mooloolaba’s natural features, with daily trips expected to increase from around 61,000 today to more than 90,000 in 2041,” Cr Natoli said.

“The upgrade to Walan Street is an important part of this future planning.

“Motorists will also benefit from better access to the new ParknGo Mooloolaba Central car park and the new signalised intersection at Walan Street and Naroo Court.

“Construction of the highly anticipated upgrade of Stages 2 and 3 of Brisbane Road to four traffic lanes will also soon begin.

“It’s wonderful we are now in a position to move onto the Brisbane Road upgrade, which presents an opportunity to enhance the gateway arrival experience into Mooloolaba.

“Thanks to the Federal Government’s $12 million funding contribution, we have brought forward the new Mayes Canal Bridge construction.”

Stages 2 and 3 will now be built concurrently, with construction starting in May 2021 and anticipated for completion in late 2022.

Councillor Natoli said the next two stages would see the widening of Brisbane Road from two lanes to four lanes, connecting to the Stage 1B Walan Street upgrade.

Dr Joe Natoli welcomes the completion of stage 1 of the Mooloolaba traffic upgrade.

“Located between Walan Street and Kyamba Court, Stages 2 and 3 will include intersection upgrades, provision for cyclists, landscaping and the new Mayes Canal Bridge,” Cr Natoli said.

“The new bridge will maintain the same waterway clearance as the current bridge and be a 26.4-metre-wide, four lane bridge with shared pedestrian and cycle paths on both sides.

“With Brisbane Road being one of Mooloolaba’s main arteries, we will keep traffic moving while we make this important upgrade.

Help keep independent and fair Sunshine Coast news coming by subscribing to our free daily news feed. All it requires is your name and email. See SUBSCRIBE at the top of this article

“Council will continue to make every effort to minimise impacts to the local community and businesses during construction however this is a major construction project and some inconvenience is to be expected.

“Residents and interested parties will be provided with advance notice of anticipated impacts and will be updated as the project progresses.”

For more information about the project, visit the project webpage at www.sunshinecoast.qld.gov.au/MTCU or phone 5475 7272.

Mooloolaba Transport Corridor Upgrade:

• The Mooloolaba Transport Corridor Upgrade widening of Brisbane Road and Walan Street, is a multi-stage upgrade project

• Stage 1A (completed in October 2019) $2 million extension of Naroo Court through to Muraban Street including a new roundabout.

• Stage 1B (completed in April 2021) $8.5 million Walan Street upgrade between Venning Street and Smith Street to four traffic lanes.

• Stage 2 (2021 – 2022) Brisbane Road from 42 Brisbane Road through to Kyamba Court including the new Mayes Canal Bridge.

• Stage 3 (2021 – 2022) Intersection of Brisbane Road/Walan Street/Hancock Street.

• Stage 4 (2023) Brisbane Road from near Bindaree Crescent to Culbara Street including Tuckers Creek Bridge.

All stages and scheduled timeframes may change subject to weather, site conditions, council’s budget process and other funding.

[scn_go_back_button] Return Home

Subscribe to SCN’s daily news email

This field is for validation purposes and should be left unchanged.