TMR expects Kilcoy-Beerwah Road at Cedarton to have both lanes re-opened by Christmas

Do you have a news tip? Click here to send to our news team.

Iconic beachfront building undergoes major upgrade

One of Noosa’s most recognisable beachfront addresses has had a top-to-bottom revitalisation. The full structural and aesthetic renewal of the 24-apartment complex, Number One in More

Coast professor details warning signs of PTSD

Feeling stressed after a traumatic event is normal, but a global post-traumatic stress disorder (PTSD) expert says there are clear signs that it may More

Park upgrades help users overcome communication barriers

Ten Sunshine Coast parks are now home to communication boards designed to make the facilities more interactive and educational. Created by Sunshine Coast Libraries in More

Fast-tracked degree to meet demand for engineers

The University of the Sunshine Coast (UniSC) is addressing Australia’s demand for highly skilled engineers by launching an accelerated pathway into its Master of More

Photo of the day: sunrise splendour

A stunning sunrise at Shelly Beach. This moment was captured by Lesley Evans. If you have a photo of the day offering, email photo@sunshinecoastnews.com.au. Photos must More

New habitats underway for endangered native fish

Trees will be used to create underwater habitat structures for endangered native fish species on the Sunshine Coast in a new initiative. The Seqwater program, More

Frustrated motorists who rely on the Kilcoy-Beerwah Road at Cedarton could still be in for a long wait to have both lanes opened on the important transport link.

While the Department of Transport and Main Roads says the work should be done this year, it’s unlikely to happen in the first half of 2024.

Member for Glass House Andrew Powell said it had already been too long – the road was impacted in early 2022 when a drain failed and half the road slipped away.

One lane was closed and traffic lights were installed to allow regulated usage of the road.

Related story: Delay dismay: works stall on landslip-affected road

Mr Powell said that was only ever intended to be a short-term fix until design and construction work could properly – and safely – mend the road.

“It’s been 698 days of locals, tourists and business operators having to sit at the lone traffic light on Kilcoy-Beerwah Road and there doesn’t seem to be a start, let alone an end, in sight for the roadworks,” he said.

A section of road impacted by landslip. Picture: Google Maps

“I understand that there are more immediate priorities following the recent cyclone and storms, but how much longer are hinterland locals going to be asked to wait?”

In a statement, TMR said it was working on a solution.

“Many sites across the region were impacted in the major flooding event of early 2022, including the section of Kilcoy-Beerwah Road at Cedarton, just south of the Maleny-Stanley River Road intersection,” a TMR spokesperson said.

“To ensure the safety of road users, approximately 200 metres of the westbound lane on Kilcoy-Beerwah Road has been closed. This closure allows for a thorough assessment of the damage, geotechnical investigations and the planning and design of repair works.

“The Kilcoy-Beerwah landslip repairs are part of a comprehensive recovery program that addresses over 100 batter slope/embankment repairs throughout the region.

“TMR has finalised a detailed design and is currently undertaking procurement for construction. Construction across the program is expected to be carried out in 2024, weather permitting.

“Traffic updates will be provided to road users once construction timeframes for the Kilcoy-Beerwah Road site are confirmed. In the interim, TMR will continue to monitor this section of Kilcoy-Beerwah Road to maintain safety until full reconstruction can be completed.”

Mr Powell said that, when asked on several occasions last year, TMR informed him rectification works would require multiple design elements due to the steep embankment failure and the high risk rating the site received during the post-flood inspection.

“I have written to the new Minister for Main Roads (Bart Mellish) to remind him of the long-overdue repairs, because from where I stand the community have just been abandoned,” he said.

TMR said the work would be funded through the joint Commonwealth-State Disaster Recovery Funding Arrangements.

Do you have an opinion to share? Submit a Letter to the Editor at Sunshine Coast News via news@sunshinecoastnews.com.au. You must include your name and suburb.

Subscribe to SCN’s free daily news email

This field is for validation purposes and should be left unchanged.
This field is hidden when viewing the form
[scn_go_back_button] Return Home
Share