Sunshine Coast rail upgrade lays groundwork for new modern trains

Do you have a news tip? Click here to send to our news team.

Falcons and Storm to end decade-long partnership

The Sunshine Coast Falcons have confirmed their long-standing feeder club affiliation with the Melbourne Storm will come to an end after the 2025 season. The More

Photo of the day: ocean paddlers

Paddlers off Kings Beach at Caloundra, by Lesley Evans. If you have a photo of the day offering, email photo@sunshinecoastnews.com.au. Photos must be horizontal/landscape and More

Lucrative prizes on the line for freshwater fish

The state’s most successful recreational fishing initiative is gearing up for a major milestone. The Stocked Impoundment Permit Scheme (SIPS) is marking 25 years, with More

Young man dies in Kandanga crash

A 19-year-old has died after a campervan veered off the roadway and crashed near Kandanga Creek bridge early on Sunday morning. Police and emergency crews More

Two dead in crash with stolen car near Gympie

Two people have died following a crash involving a stolen vehicle at Chatsworth yesterday afternoon. About 3pm, emergency services were called to a three-vehicle crash More

1000 speeding fines in Coast school zones in a year

More than 1000 speeding infringements were issued in Sunshine Coast school zones last year, prompting the rollout of new flashing signs at high-risk sites. The More

New signalling technology is being installed on the Sunshine Coast rail line which will lay the groundwork for introducing the “next generation” of modern trains.

The $45 million signalling project is described as an “autopilot” system which can “take over” control of the train from the driver and improve safety.

It comes as work is expected to start later this year on the Sunshine Coast Rail Duplication, duplicating 20km between Beerburrum and Landsborough and upgrades to Nambour.

The first phase of the $550million duplication project will include a realignment of sections of Steve Irwin Way and the installation of Park and Ride facilities at Nambour and Landsborough.

Work on the signalling project started at Gympie and is now focussed on the Nambour area as the project continues towards Caboolture.

Construction leader Ben Cue, from Rail Control Systems which is leading the project, said the signalling technology was like an autopilot for trains which could read and react to problems along the line.

About 60 workers are involved in rolling out the European Train Control System (ETCS) level one technology.

Transport and Main Roads Minister Mark Bailey said 130 signal equipment cubicles would be upgraded and 43 new equipment cubicles installed over 120 kilometres of track.

Mr Bailey said the project was not only supporting local jobs, it was also gearing up the North Coast rail line for improved services between the Sunshine Coast and Brisbane ahead of Cross River Rail opening in 2025.

“Installing ETCS technology on the line means we’ll be able to put the newer NGR (Next Generation Rollingstock) class trains into services up to Gympie,” Mr Bailey said.

“Integrating ETCS and Automatic Train Protection (ATP) systems along the line is also an important step in preparing for track duplication between Beerburrum and Landsborough.

“Once installation has been completed along the track and onboard trains, the new infrastructure will provide an engineering control to ensure trains stop before the red signal.”

The Beerburrum to Nambour Rail Upgrade is due to start towards the end of 2021.

Member for Nicklin Robert Skelton said the upgrades would enable more modern trains “which will be welcomed by the thousands of people who commute to work every day”.

“Crews started work near Gympie last September and have been progressively making their way south,” he said.

“This project will continue to support a significant number of jobs through to the middle of next year until the crews finish their work just south of Caboolture.

“Works are about to ramp up on the Sunshine Coast Rail Duplication project, so I’m pleased to see the work is being done to equip the rail line with signalling technology that is increasingly being adopted on major rail systems across the world.”

As part of the Cross River Rail project, a new signalling system is also being installed across sections of the inner-city network, using ETCS level two technology.

The works will be rolled out in several stages starting with the Shorncliffe line, where work has already started.